Da Nang accelerates US$113 million integrated adaptive development project

By MAI DUNG • 12/11/2026 11:11

DNO - Vice Chairman of the Da Nang People’s Committee Tran Nam Hung chaired a meeting on November 11 with a delegation from World Bank (WB) to review progress and address obstacles facing the Integrated Adaptive Development Project in former Quang Nam Province (now part of Da Nang).

img_9601-1-.jpeg
Vice Chairman of the Da Nang People’s Committee Tran Nam Hung speaks at the meeting. Photo: QUOC TUAN/DNRT

The Integrated Adaptive Development Project in former Quang Nam Province has a total investment of VND2.723 trillion (approximately US$113.39 million).

It is being implemented across the communes and wards of Duy Nghia, Thang An, Thang Truong, Ban Thach, Quang Phu, Tam Xuan, Tam Anh and Tam Hai.

Regarding the implementation progress of project packages, construction has begun on Binh Duong, Binh Nam and Tinh Thuy bridges, while the construction contract for Hung My Bridge has been awarded.

The Tam Thanh Bridge and Tam Ky Flood Drainage Complex projects are undergoing adjustments, while the remaining packages are at the contractor selection stage.

The project has been allocated nearly VND285 billion in capital for 2026, of which VND253 billion has been disbursed, equivalent to 88.8%. The planned capital allocation for 2027 is VND677 billion.

img_9565.jpeg
Representatives of the World Bank delegation at the meeting. Photo: QUOC TUAN/DNRT

At the meeting, the Da Nang Management Board for Transport and Agricultural Construction Investment Projects (the project owner) proposed that the city’s Land Fund Development Center urge its regional branches to step up coordination with the communes and wards in the project area.

Priority should be given to completing the inventory and preparing compensation, site clearance and resettlement plans for submission for approval, as well as handing over cleared sites in accordance with the deadlines agreed upon on October 12, 2026.

Taking into account feedback from the World Bank delegation, Vice Chairman Tran Nam Hung instructed relevant agencies to strengthen construction supervision and urgently submit livelihood support plans for communities affected by the project for the city’s approval.

dji_0817.jpeg
The Truong Giang River dredging package is still at the contractor selection stage. In the photo: A section of the Truong Giang River running through Thang An Commune. Photo: QUOC TUAN/DNRT

Relevant agencies will step up site clearance efforts, striving to complete the entire process before December 2027.

Vice Chairman Tran Nam Hung pledged that Da Nang would ensure sufficient counterpart funding in line with the approved plan and maintain disbursement, in accordance with the actual progress of each project package, with a view to completing the project on schedule.

By MAI DUNG